现浇预应力连续箱梁专项施工方案

2019-01-19 16:36

现浇连续梁施工及调流专项方案

1

现浇连续梁施工及调流专项方案

目 录

一、编制依据与原则 ............................................................................................................. 1

1编制依据 ..................................................................................................................... 1 2编制原则 ..................................................................................................................... 1 3编制范围 ..................................................................................................................... 1 二、工程概况 ........................................................................................................................ 1 三、施工准备 ........................................................................................................................ 3 四、交通调流措施 ................................................................................................................ 3 五、交通组织方案 ................................................................................................................ 8 六、现浇连续梁施工方案 ................................................................................................... 13

1施工放样 ................................................................................................................... 13 2材料 ........................................................................................................................... 13 3 机械、设备 .............................................................................................................. 13 4施工人员安排 ........................................................................................................... 14 5、施工方案及工艺流程 .............................................................................................. 14 5.1施工方案 ............................................................................................................... 14

5.2施工工艺流程 ....................................................................................................... 15 6、施工方法及技术措施 .............................................................................................. 15 6.1地基处理 ............................................................................................................... 15 6.2模板及支架的搭设 ............................................................................................... 16 6.3支架预压 ............................................................................................................... 18 6.4模板安装 ............................................................................................................... 20 6.5支座安装 ............................................................................................................... 20 6.6钢筋加工及安装 ................................................................................................... 20 6.7混凝土浇筑、养护 ............................................................................................... 22 6.8预应力张拉与管道压浆 ....................................................................................... 24 6.9模板及支架拆除 ................................................................................................... 29 七、冬季施工保证措施 ....................................................................................................... 29

1冬季施工技术措施 ................................................................................................... 30 2冬季施工安全措施 ................................................................................................... 31 八、质量保证措施 .............................................................................................................. 31 九、危险因素分析 .............................................................................................................. 32

1、危险源辨识 ............................................................................................................ 32 2、危险因素评估 ........................................................................................................ 33 十、安全施工保障措施和文明施工 .................................................................................... 34

1、安全生产管理目标 ................................................................................................ 34 2、安全生产方针 ........................................................................................................ 34

1

现浇连续梁施工及调流专项方案

3、主要安全管理制度 ................................................................................................ 34 4、保证安全施工的措施 ............................................................................................ 35 5、应急处理预案 ........................................................................................................ 35 6、文明施工 ................................................................................................................ 38

2

现浇连续梁施工及调流专项方案

现浇预应力连续箱梁施工及调流专项方案

一、编制依据与原则 1编制依据

《两阶段施工图设计》。

公路桥涵施工技术规范JTG_TF50-2011 公路工程技术标准JTG_2003 道路交通标志和标线GB5768—1999 公路养护安全作业规程JTG H30-2004

本公司拥有的施工工艺、施工方法成果、机械设备、管理水平、技术装备及多年积累的类似工程施工经验。 2编制原则

1、严格遵守招标文件明确的设计规范,施工规范和质量评定验收标准。

2、坚持技术先进性,科学合理性,经济适用性,安全可靠性与实事求是相结合。

3、对施工现场坚持全员、全方位、全过程严密监控,动态控制,科学管理的原则。 3编制范围

本方案适用于二标段现浇连续梁施工。

二、工程概况 *****项目起点位于***(桩号K27+700),终点位于***(桩号K36+500),路线全长8.8km,分三个标段施工,本项目位于二标段,起讫里程为K31+400~K34+850,共计全长3.45km。本标段跨线桥梁共三座*****,上部结构均为现浇连续箱梁.

****天桥跨径组合为25+36+36+25m,箱梁采用单箱单室断面,箱梁顶宽850cm,底宽440cm,直腹板设计,悬臂长2.05m,悬臂端部厚度20cm,

1

现浇连续梁施工及调流专项方案

根部厚度50cm,箱梁顶板厚度25cm,底板厚度22cm。腹板厚度45cm,梁高1.6m。

K31+547天桥

****跨径组合为25+30+30+25m,上部结构采用双幅箱梁断面,双幅之间设1cm纵缝,单幅箱梁为单箱三室结构,箱梁顶宽15.74m,底宽13.745m,直腹板设计,悬臂长度2m,悬臂端部厚度20cm,根部厚度50cm,箱梁顶板厚度25cm,底板厚度22cm。腹板厚度45cm,梁高1.6m。

K33+177即威分离立交半幅

****互通立交跨线桥,跨径布设采用25+40+40+25m,本桥采用左右幅分别施工,其中左、右幅桥箱梁为单箱三室断面,箱梁顶宽12.75m,底宽10m,直腹板设计,外侧悬臂长度2m,内侧悬臂长度1.25m。箱梁顶板厚度均为25cm,底板厚度为22cm,腹板厚度为45cm,跨中梁高160cm,墩顶梁高为230cm,抛物线变高。左右幅间预留1m后浇带,待左右幅桥预应力施工完成后,通过后浇带施工将两幅桥进行横向连接。

2


现浇预应力连续箱梁专项施工方案.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:建筑设计企业质量管理体系表格

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: