郑州至西安客运专线基础工程沉降观测指导方案(2)

2019-01-12 18:53

4、 变形测量点分为基准点、工作基点和变形观测点。其布设应符合下列要求: Deformation measure points are classified into datum marks, work basic points and deformation observation points. The layout of them should accord with the following requirements:

(1) 每个独立的监测网应设置不少于3个稳固可靠的基准点,且基准点的间距不大于1公里。基准点应选设在变形影响范围以外便于长期保存的稳定位置。使用时应作稳定性检查与检验,并应以稳定或相对稳定的点作为测定变形的参考点。

Each independent observation net should set no less than 3 steady datum marks, and the space between datum marks should be within 1km. The datum marks should be set out of deformation scope, which is easy to long term keep. When using, should check the stability, and make the stable or comparatively stable points as the referent points for measuring deformation.

(2) 工作基点应选在比较稳定的位置。对观测条件较好或观测项目较少的工程,可不设立工作基点,在基准点上直接测量变形观测点;

Work basic points should be set at a stable place. For the engineering which has better observation conditions and less observation projects can directly measure deformation observation points at datum marks, without setting work basic points.

(3) 变形观测点应设立在变形体上能反映变形特征的位置。

Deformation observation points should be set at a place which can reflect deformation characters.

5、 每次观测前,对所使用的仪器和设备,应进行检验校正,并保留检验记录. Before observation, check and revise the instrument and facility, and save the checking record.

6、 在沉降观测基准网建立后,应对水准基点做好保护工作,发现丢桩或桩位有移动现象,应尽快恢复和补测桩点。另外,应定期对沉降观测基准网进行复测,提出复测成果,复测周期不大于6个月。

After establishing settlement observation norm net, should protect well level basic points. If find pier missing or moved, should recover and measure it as soon as possible. What’s more, should regularly remeasure settlement observation norm net and raise remeasuring results. The remeasuring period should be no more than 6 months.

日期:2007-01-09 Date:2007-01-09

翻译: Translated by:

芦丽萍,王瑾,朱荣,巩亚强 Sophy, Vivian, Michelle, Simon

审核 proofread

Page 6 of 85 7、 应使用精度不低于DSZ1的自动安平水准仪或DS1的气泡式水准仪,水准标尺应采用与之配套的带有两排分划的线条式铟瓦合金标尺,水准仪和水准标尺各项技术指标应符合《国家一、二等水准测量规范》(GB12879-91)有关规定,在沉降观测前和沉降观测过程中的规定时间段应对仪器和标尺进行检定。 Should use the automatic level, precision of which is no less than DSZ1, or use the bubble level DS1. The level rod should use two rows indium alloy staff gauge. Every technical criteria of water level and level rod should accord with National First and Second Level Measure Regulations(GB12879-91), facilities and rods should be checked before settlement observation and at the specified slot of settlement observation.

8、 沉降观测置镜点、观测路线、观测人员、观测设备一般应固定,在成像清晰稳定的条件下进行观测,不得在日出后及日出前约半小时及其他不宜观测的天气情况下作业;作业中应经常对水准仪及水准尺的水准器和i角进行检查;在同一测站观测时,不得两次调焦,以确保观测成果的质量。

Mirror place of settlement observation, observation routes, observers, observation facilities should be fixed. Observe under the clear and stable imaging condition, don’t after sunrise, half an hour before sunrise, and other weather which isn’t good for observation; should frequently examine level tube and i angle of level instrument and level rod; in order to make sure the quality of observation results don’t focus two times at the same observation station.

9、 每一项目的工程变形测量任务完成以后要及时进行测量成果整理, 应提交下列综合成果资料:

After finishing engineering deformation measure of each project, clear up the results in time, and hand in the following data of integrated results:

(1)施测方案与技术设计书; measure scheme and technique design (2)控制点与观测点平面布置图; layout plan of reference points and observation points

(3)标石、标志规格及埋设图;markstone, mark standard, and embedded drawing

(4)仪器检验与校正资料;check facilities and revise data (5)观测记录手簿;observation record notebook

日期:2007-01-09 Date:2007-01-09

翻译: Translated by:

芦丽萍,王瑾,朱荣,巩亚强 Sophy, Vivian, Michelle, Simon

审核 proofread

Page 7 of 85 (6)平差计算及测量成果表;balance calculation and measure results list (7)变形过程和变形分布图表;deformation process and layout plan (8)变形分析成果资料;data of deformation analysis results (9)变形测量技术报告。deformation measurement technique report

四、 路基subgrade

(一)一般规定general regulation

1、 观测的目的是通过沉降观测,利用沉降观测资料分析、预测工后沉降,提出加速路基沉降的措施,确定无碴轨道的铺设时间,评估路基工后沉降控制效果,确保无碴轨道结构的安全。The purpose of the observation is after settlement observed, used the settlement observation data to analyze and forecast the after work settlement, put forward the measure, which increase the subgrade settlement, ensure the slab track installed time, estimate the subgrade after work settlement control effect and ensure the slab track structure safety.

2、 路基上无碴轨道铺设前,应对路基变形作系统的评估,确认路基的工后沉降和变形满足无碴轨道铺设要求。Before install the slab track, it shall systemic assess the subgrade deformation to affirm the subgrade after work settlement and deformation can satisfy the slab track installation requirement.

3、 路基填筑完成或施加预压荷载后应有不少于6个月的观测和调整期。观测数据不足以评估或工后沉降评估不能满足设计要求时,应延长观测或采取必要的加速或控制沉降的措施。After finished filling or preloading, it shall have more than 6 months observation and adjustment period. When the observed data is not sufficient to assess the settlement or the after work settlement can not satisfy the design requirement, it shall be extended the observation time or adopted the necessary measure to increase or control the settlement.

4、 观测期内,路基沉降实测值超过设计值20%及以上时,应及时查明原因,必要时进行地质复查,并根据实测结果调整计算参数,对设计预测沉降进行修正或采取沉降控制措施。In the observation period, when the actual measured settlement exceed more than 20% of the design value, it shall clarify the reason, when necessary it shall recheck the geology, and according to the actual measured result to adjust the calculation parameter, modify or adopt the settlement control measure for the design

日期:2007-01-09 Date:2007-01-09

翻译: Translated by:

芦丽萍,王瑾,朱荣,巩亚强 Sophy, Vivian, Michelle, Simon

审核 proofread

Page 8 of 85 forecast settlement.

5、 评估时发现异常现象或对原始记录资料存在疑问,要进行必要的检查。When assess, if it will appear the abnormal appearance or exist the doubt for the original recorder data, it shall be checked.

(二)观测的内容the content of the observation

1、 路基沉降观测应以路基面沉降和地基沉降观测为主。The subgrade settlement observation shall mainly observe the subgrade surface settlement and foundation settlement

2、 路堑沉降观测部位为基床表层的底面处。The cutting settlement observation part is the bottom surface of the bedding surface layer.

3、 路堤沉降是由路堤本体和地基组成,为了观测到路堤的沉降与时间的关系,及沉降主要产生的部位,一般路堤观测的内容应为:基床底层顶面的路基总沉降和地基面处地基部分总沉降。The embankment settlement is caused by embankment and the foundation. To observe the relationship between the settlement and time of the embankment and the main part that caused the settlement, generally the embankment observation content is: the subgrade total settlement of the bedding bottom layer surface and the foundation part total settlement of the foundation surface. 4、 对于地基条件复杂和填土高度大的路堤,还包括如下内容:路堤中部的沉降观测;地基处理范围的下限处地基深部的沉降观测。For the embankment that the foundation condition is more complex and the filling is higher, it shall be also contained the following content: the settlement observation in the middle part of the embankment; in the foundation treatment range the lower limit part, the settlement observation of the foundation depth.

(三)观测断面和观测点的布置set the observation cross section and observation point

1、观测断面布置set the observation cross section

(1) 路基沉降观测断面的设置及观测断面的观测内容应根据地形地质条件、地

基处理方法、路堤高度、堆载预压等具体情况,结合沉降预测方法和工期要求具体确定。

The setup of subgrade settlement observation cross section and the observation content of the observation cross section shall follow the landform and 日期:2007-01-09 Date:2007-01-09

翻译: Translated by:

芦丽萍,王瑾,朱荣,巩亚强 Sophy, Vivian, Michelle, Simon

审核 proofread

Page 9 of 85 geological condition, foundation treatment method, height of the embankment, preloading etc, and combine with the settlement forecasting method and the work time requirement to determine.

(2) 沉降观测断面的间距一般不应大于50 m。地形、地质条件变化较大地段应

适当加密(以设计文件为准),应不大于25m布设一个断面。

Generally, the distance between the observation cross sections is no larger than 50m, if the foundation condition is complex, the landform is changed a lot (the design document as a standard) it shall be increased, every 25m it shall be set one cross section.

(3) 一个沉降观测单元(连续路基沉降观测区段为一单元)应不少于2个观测

断面。

In one settlement observation unit (continuous subgrade settlement observation section is one unit), it is no less than 2 observation cross sections. 2、观测点布置set the observation point

(1) 沉降观测可在线路两侧地基、路肩和线路中心设置观测桩;在地基和基床

底层的顶面设置剖面沉降管,或在线路中心设置沉降板。

The settlement observation can be set on the foundation, shoulder at the two sides of the line and in the center of the line it can be set the observation pile. On the surface of the foundation and the bedding bottom layer it shall be set the profile settlement pipe, or in the center of the line shall be set the settlement board.

(2) 对于路堤观测断面,在线路中心线布设一组沉降板,路肩两侧布设变形观

测桩。对地形横向坡度大或地层横向厚度变化的路基工点应布设不少于1个横向观测断面,每个断面3组观测点。

It shall be set one group settlement board on the alignment center line for the embankment observation cross section, on the two sides of the shoulder it shall be set the deformation observation pile. For the subgrade work area that the landform cross direction gradient is larger or the stratum cross direction thickness changed, it shall be set more than 1 cross observation section, every cross section shall contain 3 group observation points.

(3) 有预压土路堑地段,每个路堑断面在线路中心设沉降板一组,两侧路肩各

日期:2007-01-09 Date:2007-01-09

翻译: Translated by:

芦丽萍,王瑾,朱荣,巩亚强 Sophy, Vivian, Michelle, Simon

审核 proofread

Page 10 of 85


郑州至西安客运专线基础工程沉降观测指导方案(2).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:中国百强校福建省厦门市双十中学2017-2018学年度初一下数学期末

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: