蕉门河中心区双桥项目车行桥深基坑专项施工方案
目 录
1.编制范围、依据 ........................................................................................................... 1 1.1编制范围 ......................................................................................................................... 1 1.2编制依据 ......................................................................................................................... 1 2.工程概况 ...................................................................................................................... 1 2.1工程概述 ......................................................................................................................... 1 2.2工程场地自然条件 ......................................................................................................... 2 2.3施工难点分析 ................................................................................................................. 5 3.施工危险源辨识 ........................................................................................................... 6 4.基坑开挖支护、支撑体系设计 ..................................................................................... 6 4.1基坑支护、支撑结构选型 ............................................................................................. 6 4.2基坑支护设计及力学检算 ............................................................................................. 7 5.总体施工安排 ............................................................................................................... 7 5.1施工工期安排 ................................................................................................................. 7 5.2机械设备投入计划 ......................................................................................................... 7 5.3劳动力投入计划 ............................................................................................................. 8 6.深基坑支护施工工艺及施工方法 ................................................................................. 8 6.1深基坑施工工艺流程 ..................................................................................................... 8 6.2拉森钢板桩施工 ............................................................................................................. 9 6.3基坑开挖及支护 ........................................................................................................... 13 6.4基坑排水 ....................................................................................................................... 13 6.5承台施工 ....................................................................................................................... 14 7.基坑观测及检测 ......................................................................................................... 14 8.深基坑施工质量保证措施 .......................................................................................... 15 8.1质量目标 ....................................................................................................................... 15 8.2质量保证体系 ............................................................................................................... 15 8.3质量保证措施 ............................................................................................................... 16 9.深基坑施工安全保证措施 .......................................................................................... 17 9.1 安全管理目标及原则 .................................................................................................... 17 9.2 安全管理组织保证体系 ................................................................................................ 17 9.3安全保障措施 ................................................................................................................ 17 10.文明施工及环境保证措施 ........................................................................................ 20 10.1文明施工措施 ............................................................................................................. 20 10.2环境保护主要采取的措施 ......................................................................................... 20 11.深基坑施工应急预案 ................................................................................................ 21
1
蕉门河中心区双桥项目车行桥深基坑专项施工方案
11.1 应急组织、指挥系统 ................................................................................................. 21 11.2 应急预案启动 ............................................................................................................. 23 11.3 预防、应急处置措施 ................................................................................................. 23 11.4 应急物资保障 ............................................................................................................. 26 12.附件: .......................................................................................................................27 12.1基坑支护平面图 ......................................................................................................... 28 12.2基坑支护立面图 ......................................................................................................... 29 12.3基坑支护检算书 ......................................................................................................... 30
2
蕉门河中心区双桥项目车行桥深基坑专项施工方案
蕉门河中心区双桥项目
车行桥1、2#主墩深基坑专项施工方案
1.编制范围、依据
1.1编制范围
广州南沙新区蕉门河中心区双桥项目—车行桥1、2#主墩承台深基坑施工。 1.2编制依据
(1) 《蕉门河中心区双桥项目施工图设计——车行桥》(四川西南交大土木工程设计有限公司);
(2)《公路桥涵施工技术规范》(JTG /T F50-2011); (3)《公路工程质量检验评定标准》(JTG F801-2012); (4)《建筑基坑支护技术规程》(JGJ120-2012); (5)《建筑基坑工程监测技术规范》(GB50497-2009); (6) 其它施工、安全相关规范规定。
2.工程概况
2.1工程概述
蕉门河中心区双桥项目—车行桥位于广州南沙新区,车行桥西连南府路,跨越蕉门河后,东接金岭一横路。桥梁长 231 米,桥宽 25.6 米。
该桥采用外倾式非对称吊杆拱桥结构,梁部为钢箱梁。主、副拱分别绕旋转轴向面外旋转 16 度、18 度而成。左侧拱肋名义跨径为75.5+155.5=231 米,右侧拱肋名义跨径为 55.5+175.5=231 米。左侧拱肋的主跨跨径 155.5m,面内矢高 44.955m,矢跨比 1/3.459。右侧拱肋主跨 175.5m,面内矢高 54.641m,矢跨比为 1/3.212。拱肋采用六边形钢箱结构,拱肋主材材质为Q370qD-Z25钢板。
全桥共设 44 根吊杆,左侧拱肋设置 20 根,右侧拱肋设置 24 根。吊杆纵向间距为 6m。全桥布置四根永久的柔性系杆,系杆规格为 PESFD7X-163,每个拉索均由 163 束 7mm 镀锌热挤聚乙烯高强钢丝组成。
钢箱梁采用正交异性板流线型扁平钢箱梁,梁高 2.0m,宽(含风嘴)25.6m;钢箱梁总长 235 米,钢箱梁划分成 58 个节段。梁体标准节段长为 4m,运抵现
1
蕉门河中心区双桥项目车行桥深基坑专项施工方案
场后组拼成12m 的吊装节段以便安装。
1、2号主墩下部结构采用整体承台群桩基础,每个承台下共15根φ2.0m钻孔灌注桩;承台平面尺寸为31.2x15.2m,承台厚 4.0m,与线路中心线垂直布置。承台顶拱座高3.0m,平面尺寸为 14.6x9.0m的拱座,拱座顶以下 1 米处预埋有锚固钢板与拱肋连接成整体受力。主墩设置在线路中线附近,为倒三角形,其顶面尺寸为 11mx2m,与承台连接底面尺寸为 4x2m。0、3 号边墩下部结构根据受力大小确定基础形式,0 轴右侧、3轴左侧拱肋采用群桩基础,单个承台下设 9 根φ1.8m 钻孔灌注桩,承台平面尺寸为12x12m,高 3m;0 轴左侧、3 轴右侧拱肋也采用群桩基础,单个承台下设 9 根φ1.2m钻孔灌注桩,承台平面尺寸为 9.4mx9.4m,高2m,承台顶设置拱座支撑端横梁,拱座高1.8m。
全桥下部结构共设置0、3#两个桥台,0、3#两个边墩,1、2#两个主墩(详见附图1—总体布置图)。桩基利用草袋围堰筑岛进行施工,由于本桥所处区域常水位为5.2米,围堰筑岛平台标高为5.9m。
蕉门河中心区双桥项目车行桥桩基承台结构形式统计表
桩基 围堰桩工程 部位 第一第二层:人m 根 m m m m 工填泥,m 砂土,m 土,m 1#主墩 2 2#主墩 2 15 31.2×15.2×4.0 15 31.2×15.2×4.0 5.5 5.5 -3.6 9.10 -3.6 9.10 1.4 1.9 21.1 9.05 5.2 层:淤淤泥质第三层:数结构尺寸 径 量 高 高 深度 100KPa) 顶标底标开挖泥50KPa,淤泥质砂土承台 基坑内地质情况及容许承基坑基坑载力(人工填土100KPa,淤
2.2工程场地自然条件
2.2.1地形地貌
本项目为海陆交互相冲积平原地貌,场地地表水较发育,拟建桥梁跨越蕉门
2
蕉门河中心区双桥项目车行桥深基坑专项施工方案
河,水深 0.40~7.80 米,受潮汐影响,河水面标高 3.16~6.71 米,河床断面呈 U 形,河道平直,由北向南流,流速中等,侵蚀作用不明显。两岸为Ⅰ级阶地,地貌单元属于珠江三角冲积平原。根据《工程自然区划标准》,该区属于华南沿海台风区(Ⅳ7)。
2.2.2气象
地属南亚热带季风气候,具有温暖多雨、阳光充足、温差较小、夏季长、霜期短等气候特征。年降雨量为 1689~1877mm,雨量集中在 3~9 月,雨季降雨量占全年的 85%左右。年蒸发量 1600~1700mm。本区夏季多东风及东南风,冬季多东北风,年平均风速 2.4m/s,每年8~11 月常有强热带风暴,极端最大风速可达 40m/s,台风为本地主要自然灾害。年平均气温22.1℃,平均气温 7 月最高,为 28.2℃,1 月最低,为 13.4℃。
2.2.3水文
河流属平原河流,水流平缓,潮汐明显,潮差平均为 2.4m,主要河道为沥窖水道、沙湾水道和蕉门水道。蕉门水道通过本场地,场地中有较多鱼塘。河涌两头均设有水闸,在入小虎沥前有蕉东闸,位于东湾闸出口以南,但此闸现因工程老化严重,运行状况不佳,规划更新重建,新闸闸址选在现状闸址以北(外移);南通蕉门水道,有蕉西闸控制,为近年新建水闸,规划保留加固达标,现状水闸运行水位 5.00~6.00m。蕉门河常水位约为5.2m。
沿线地下水主要赋存于海陆交互相沉积淤泥质粉砂层<②-2>,深部地下水主要赋存于基岩裂隙内,地下水类型按赋存条件分为上层滞水、第四系孔隙水(潜水)和基岩裂隙水两种。上层滞水主要分布在第四系人工填土层中。人工填土层结构疏松,含上层滞水,该层含水量有限,地下水动态受季节降雨影响。海陆交互沉积之淤泥质粉砂为含水层,含孔隙水,具承压性,含水量贫乏~中等。场区内孔隙水矿化度高,大多为微咸水或半咸水,不能作为生活饮用水。场地的地下水位埋深一般 0.00~2.80m。场地环境类型为 II 类,渗透类型为 B。按《岩土工程勘察规范》(GB 50021-2001)( 2009年版)第 12.2 条有关标准判定:本场地地下水对混凝土结构有微腐蚀性,对干湿交替带混凝土结构中钢筋有微腐蚀性。土对混凝土结构有微腐蚀性,对干湿交替带混凝土结构中钢筋有微腐蚀性,对钢结构有微腐蚀性。
2.2.4工程地质